Groupe Kelly / Sanivac — 40,000 sq. ft. asphalt project
An active commercial property, a parking lot to refresh and a tight schedule. PolyScellant maintained access, protected neighbouring vehicles and completed the sealing in one day.
40,000 sq. ft. of asphalt · 2,200+ linear feet of cracks treated · Access maintained · 14-hour single-day turnaround
REQUEST A COMMERCIAL QUOTE →BEFORE THE WORK
L’Île-Perrot, Québec | August 2026 — 40,000 sq. ft. of asphalt · Over 2,200 linear feet of cracks treated · One-day execution
A major project at Groupe Kelly’s new headquarters
In August 2026, PolyScellant had the opportunity to help enhance the grounds of Groupe Kelly / Sanivac, a Québec business specializing in environmental, sanitary and industrial services.
Located at 30 boulevard Don-Quichotte in L’Île-Perrot, the building had previously been a car dealership and was now home to the group’s administrative operations. With approximately 40,000 square feet of asphalt, the assignment called for thorough preparation, careful coordination and efficient execution. The objective was to give the parking lot a clean, dark and refreshed appearance while maintaining the existing pavement.
A thorough assessment and a clearly defined scope
After discovering PolyScellant through Google, Groupe Kelly / Sanivac contacted our company to assess its parking lot. Shanelle handled the initial discussions and first site meeting, while the team followed up with technical assessments and a detailed proposal. A second on-site meeting clarified the project requirements. After considering several contractors, the client selected PolyScellant on the basis of a well-defined scope and thorough preparation.
A parking lot requiring careful attention
Years of commercial use had left the pavement with extensive cracking, previous repairs and wear associated with vehicle traffic. During our assessment, we measured approximately 2,600 linear feet of cracks.
Renovations were also underway around the building. Before PolyScellant arrived, the client coordinated localized asphalt patching, mechanical sweeping and pressure washing by other contractors. Following discussions about priorities and the project scope, more than 2,200 linear feet of cracks were ultimately treated with hot rubber sealant.







DURING THE WORK
Planning around an occupied building
One of the biggest challenges was operational: employees still needed access to the building throughout the job. Closing every entrance at once was not an option. PolyScellant organized the sealing in stages, keeping one entrance available while another was temporarily closed. Access through the adjoining property helped manage vehicle movement, and the remaining entry area was completed last.
Protecting vehicles at the neighbouring dealership
A car dealership immediately beside the property had vehicles parked near the shared fence. To prevent sealer overspray from reaching them, our crew purchased and installed protective tarps along approximately 100 feet of fencing. The tarps were repositioned as work progressed. Protecting the neighbouring property was a central part of the project plan.
Material logistics planned weeks in advance
The large site required a significant supply of professional Black Mac sealer. To meet the work window and avoid interruptions, PolyScellant planned the quantities and on-site replenishment in advance.
Materials were prepared and delivered the evening before the project. Our on-site refilling process kept the application moving without repeated supplier trips, saving approximately eight hours of travel on the workday. For the customer, that meant a more efficient job with fewer disruptions.
Efficient execution within the planned work window
On August 26, 2026, at 4:30 a.m., the PolyScellant team began hot-rubber crack sealing to help limit water infiltration into the pavement. More than 2,200 linear feet of cracks were treated before asphalt sealing began.
At approximately 12:30 p.m., the team moved on to applying professional Black Mac sealer. Work progressed according to the access and protection plan, with the aim of completing the full application in one day for a consistent finish.
During the project, Benjamin, a representative of Groupe Kelly / Sanivac, commented on Max’s work pace with a spontaneous remark: “T’es une machine!” (“You’re a machine!”)
By approximately 6:30 p.m., after a 14-hour workday, the project was complete. Coordinating the client meetings, proposal, material supply and on-site execution allowed PolyScellant to meet its objective: complete the sealing in one day while keeping the building accessible.





AFTER THE WORK
A result noticed by the client
During the work, representatives of Groupe Kelly / Sanivac followed the progress and shared positive feedback with our team. Members of management also acknowledged the quality of the work and the crew’s efficiency.
By the end of the project, the parking lot had a dark, uniform and well-maintained appearance that enhanced the overall presentation of the property. The client expressed satisfaction with the completed work.
A project that reflects our approach
This assignment was about more than treating a large asphalt surface. It meant understanding the client’s objectives, anticipating access constraints, preparing the supply strategy, protecting neighbouring property and executing each step with care.
From the initial assessment through the final application, PolyScellant focused on the property’s needs: access, protection of neighbouring vehicles, efficient coordination and a professional finished appearance. That customer-first approach guides our commercial asphalt work.







Planning parking lot maintenance?
PolyScellant recommends site-specific asphalt maintenance solutions.